panbio-prod Migration Plan
Pan.bio · production move · execution plan · 21 Oct 2026 · second revision after review

Moving production from infrastructure-385413 to panbio-prod

What exists, what the new project looks like, what changes in code, secrets and CI, how the database moves with minutes of downtime, how the org drives are copied ahead and switched on the same night, and how the old production is deleted at the end. Each step names the Sprinto checks it closes. Effort is in engineer-days.

Source project infrastructure-385413Target panbio-prod (183358987402)Dev, Dammam, Qatar stayOrg buckets copied ahead, switched on the nightLegacy buckets deletedOld prod decommissionedCMEK onCutover incl. buckets 30 to 35 engineer-daysTwo-week sprint section 16Two review passes of 21 Oct folded in, section 17
Evidence: ~/sprinto-evidence/06-prod-migration/ (gcp-inventory.md, code-inventory.md, classification.md, Yahia's sizing note)